Litchfield to Darwin – construction in 2024
- Resurface Hwy 12 between N Armstrong Ave in Litchfield to east of Meeker CR 14 in Darwin
- Upgrade sidewalks, including pedestrian ramps, along the project area to meet ADA standards in Litchfield and Darwin
- New sidewalk will be created between Davis Ave and Hubbard Ave in Litchfield
- Replace culvert at the county ditch east of the intersection of Hwy 12 and Meeker CR 34 in Litchfield. This will require a short detour for approximately 2 weeks in 2024.
- Install pedestrian push button station at Davis St
Darwin to Cokato – construction in 2024-2025
- Repair the concrete between east of Meeker CR 14 (Darwin) to the end of the concrete section in Cokato
- Upgrade sidewalks and pedestrian ramps in Dassel to meet ADA standards
- Make ADA improvements to sidewalks and resurface the Darwin Rest Stop
- Ramps along the trail between Dassel and Cokato will be made to meet ADA standards